Riga HPP
Location: Riga HPP, Salaspils rural territory, Salaspils municipality
Status: The project was comissioned in 2018
Customer: Latvijas Valsts ceļi SJSC and Latvenergo JSC
About the project: Within the framework of reconstruction works, the LNK Industries JSC executes rebuilding of the surfacing structure, change of the road equipment and reconstruction of low-voltage and rainwater sewerage networks on Riga bypass (Salaspils — Babite) 0.30–2.38 km section of the A5 motorway. The rebuilding of the hydroelectric power plant (HPP) drainage system is being executed as well – the old drainage pipe located at a depth of 6 m will be replaced with a new one, and the duplicate drainage will be filled.

Two-level crossroad across railway tracks in Klaipeda
Location: Klaipeda, Lithuania
Status: The project put into commission in 2016
About: The flyover including premises is 330 metres long, an equivalent of more than three football pitches length. The overlay structure required 550 tons of metal constructions and 3296 cubic metres of concrete to be built. Metal structures of the overlay were fabricated by subsidiaries of LATVIJAS TILTI. In order to complete the flyover project there was also a need to relocate the engineering networks that were on the site.

Two bridges over the Pirita River, Nehatu
Location: Nehatu village on the border with Tallinn, Estonia
About: The period of construction of the bridge is divided into four stages. This ensures uniform traffic, as well as the possibility of dismantling old bridges and building new ones.
1st stage
A temporary bridge and an asphalted bypass road are built next to the existing two bridges in the lower reaches of the river.
2nd stage
Narva-Tallinn traffic is redirected to the temporary bridge and bypass road. Traffic in the Tallinn-Narva direction is redirected to the Nehatu 2 bridge currently ensuring traffic in the Narva-Tallinn direction. Thus, the Nehatu 1 bridge (currently providing traffic in the Tallinn-Narva direction) and its access ways will be freed of vehicles.
3rd stage
All traffic in the Tallinn-Narva and Narva-Tallinn directions occurring at stage 2 is redirected to the new wide Nehatu 1 bridge. Thus, the Nehatu 2 bridge and its access ways will be freed of vehicles. The temporary bridge will be dismantled. A new Nehatu 2 bridge and its access ways will be built.
4th stage
Both bridges and their access ways are built and traffic is happening in both directions via 3 +3 lanes. In accordance with the permanent traffic scheme for Tallinn-Narva direction, the road shall be converted from four-lane into three-lane at 3 stage.

Bridge for pedestrians and cyclists across Riga-Ventspils highway
Location: Riga-Ventspils highway, Latvia
Status: Construction in progress, works are scheduled for completion next summer.
About: The new overpass is located on the highway Riga – Ventspils, 14.8 kilometre, and is intended to ensure traffic for pedestrians and cyclists across the multilane A10 motorway. The bridge is a three-span steel cable-stayed bridge and its width is up to 3.4 m.
The bridge rests on 18 reinforced concrete pillars, with 52 drilled piles in the foundation. Cables of the pedestrian bridge are made of steel bars. Pedestrian bridge lighting is installed in the railing structures. Pavements are built on both sides of the pedestrian bridge too. A 50 m high fence is built on the motorway dividing strip on each side of the bridge.

Dienvidu Bridge
Location: Riga, Latvia
Status: The project put into commission in 2010
About: The largest construction project in the modern history of Latvia. Dienvidu Bridge is a 7 km long transportation system (the bridge itself and a modern system of overpasses).
- Length: 803 m
- Width: ~ 34 m
- Weight of bridge metal structures: ~ 6266 tonnes

Drawbridge over the River Venta
Location: Ventspils, Latvia
Status: The project put into commission in 2010
About: The bridge across the river Venta was put into operation in 1963. The middle section of the bridge was constructed as capable of being lifted, but because of technical problems the bridge could not be used as a lift bridge. The bridge reconstruction started in August 2009, featuring building of a new beam, carriageway and middle section, as well as repair and strengthening of the pillars. When complete, the totally rebuilt bridge is widened to provide additional vehicle capacity on the bridge. It now has a two-lane dual carriageway with a cycle path and footpaths. The bridge is 280m long and it has a 32-meter-long middle (movable) section.

Akmens Bridge
Location: Riga, Latvia
Status: The project put into commission in 1957 under the name of Oktobra Bridge.
About the project: In 1992 the bridge was renamed to Akmens Bridge. Total length of the bridge is 503.12 m. Tram, trolleybus, bus and car traffic us carried out on the 27.5 m wide carriageway. 3.5 metre wide pedestrian pavements, the railing of which is decorated with ornaments, are on the bridge sides.

Salu Bridge
Location: Riga, Latvia
- total length of the bridge across the River Daugava - 565 m,
- number of spans – 7;
- total length of the bridge across the River Maza Daugava - 230 m,
- number of spans - 3

Overpass in Avaz
Location: Avaz, Turkmentistan
Status: The project put into commission in 2011
About: Overpass on the motorway from the airport of Turkmenbashi city to the National Tourist Zone “Avaza”.

Vansu Bridge
Location: Riga, Latvia
Status: The project put into commission in 1981 as the Gorky Bridge.

Dzelzcela Bridge
Location: Riga, Latvia

Pedestrian bridge over the River Amata
Location: Latvia
Status: The project put into commission in 2004
About: The bridge span structure consists of two steel arches and a pavement, which rests on steel ties.
Bridge length is 38 m
Pavement width is 2.25 m
Arch span length is 33.4 m
Elevation 5.2 m

Venstpils Free port 1st pier dismantling
Location: Latvia
Status: Dismantling was completed in 2014.
About: 1st pier of the port of Ventspils for handling of oil and oil products was designed and built from 1959 to 1961. Its total length is 300 meters, including the mooring piles. Because of the long operation time, its structures have corroded and could no longer protect water area from oil product contamination. Demolition of the 1st pier began in February 2013.

Highway and overpass in Vilnius

Panemunes detour road
Adress: Panemune, Lithuania.
Status: The project will be put into commission in Summer 2015
About: Panemune (Lithuania) – Sovetsk (Russia) route includes highway, overpass and bridge construction across the River Neman in Panemune, Lithuania.

25th berth in the Free Port of Ventspils
Adress: Ventspils, Latvia.
Status: put into commission in 2015.
About: Within the berth reconstruction project was performed a major repair of hydraulic structures, as well as decoration of port’s surroundings. Decoration features interesting shapes that symbolize sea waves. They are constructed using concrete sustaining walls with special texture, which are paved with granite blocks. A parking lot for 39 vehicles was built on surrounding territory.

Piers of Klaipeda port
Location: Klaipeda, Lithuania
Status: launched at the end of 2013.
About the project: Multifunctional terminal in the Port of Klaipeda – the largest in Lithuania. It is equipped with unique automated Ro-Ro ramp for ship service.

12 moorage
Location: Ventspils, Latvia
Status: The project put into commission in 2015
About the project: The project includes dredging works near the pier, construction of pavement, railway reconstruction and improvement of the territory.

Riga Fertilizer Terminal
Location: Riga Freeport territory, Kundzinsala, Latvia
Status: launched at the end of 2013.

Baltic Coal Terminal
Location: Ventspils, Latvia
Status: The object was commisioned in 2009
About the project: Baltic Coal Terminal is one of the most modern terminals in Europe. This coal transhipment and storage terminal capacity is 6 million tons per year. It includes a warehouse with total area of 30,000 m2 and height – 50 m, approx. 4 km long transportation system, connecting the warehouse to the ship terminal, as well as a 300 m long deep-water pier. Terminal technology allows transhipment of 400 wagons a day in all weather conditions, while cargo transportation is carried out entirely in a closed manner, which meets environmental protection requirements.

Alpha Osta
Location: Riga, Latvia
Status: The object has been put into operation
Alpha Osta is a stevedore of the Freeport of Riga.

Riga Bulk Terminal
Location: Riga Freeport territory, Kundzinsala, Latvia
Status: The object has been put into operation in 2014
About: The most state-of-the-art terminal in the Baltic states, equipped applying technologically innovative solutions that allow the handling of eight different types of bulk cargo. Riga Bulk Terminal is unique for its engineering solutions that were used for the first time in Latvia. Construction of the terminal was launched in July 2012, and it was completed in a record short time.

Klaipeda passenger and ferry terminal
Location: Klaipeda, Lithuania
Status: launched at the end of 2013.
About:
> Each ramp weighs more than 500 t (including hydraulic equipment)
> Length of each ramp – 31.6 m
> Width of each ramp – 30.4 m
> Height of columns supporting the ramp – 11 m above the water level
> Ramp can change its position (move its edge down/up by 4.6 m)
> Ramp control is automated
> Ramp can provide service for car trailers with weight up to 140 t
> Area of each ramp is more than 900 m2 (including roadway and pedestrian area)

Quicklime transhipment terminal
Location: Liepaja, Latvia
Status: The object has been put into operation in 2012
About: Liepaja port quicklime transhipment and storage terminal. Transhipment from wagons into tanks and motor vehicles is carried out entirely in a closed manner, thus preventing environmental pollution risk and deterioration in properties of lime as a result of atmospheric influence. The project has met the customer's requirements to keep cargo fractional composition. In addition to the construction, the terminal is equipped with a lime acceptance and transhipment transportation system and automated control system. The terminal is compact, built in full compliance with customer requirements. Technical decision of the second lime transhipment system is based on the technologies that do not harm the environment.

Grand Stage at Mežaparks
Location: Mežaparks, Riga, Latvia
Status: In the process of construction
Description: The first phase of the Grand Stage at Mežaparks reconstruction project involves reconstruction of the audience area before the 2018 Latvian Song and Dance Festival.

Daugava stadium
Location: Augšiela 1, Riga, Latvia
Status: In the process of construction
Description: The project involves renovation of existing tribunes and construction of new tribunes, increasing the number of sitting places for the audience to 10,000 seats. The project is due for completion in May 2018.

Baltijas Industriālais Parks. Third expansion stage
Location: 7 Piedrujas Street, Riga, Latvia
Status: The project put into commission in 2017
About the project: Baltijas Industriālais Parks (BIP) is one of the most notable complexes of storage, office and retail premises as well as manufacturing facilities in Riga. B-class technology park. Overall area of the complex after third expansion stage – 28,000 m2. Area of the territory – 5 hectares.

reconstruction of historical building on Alberta St.

Park Inn by Radisson Riga Valdemara

River Breeze Residence
Location: 28 Kugu Street, Kliversala, Riga.
Status: Construction in progress
Description of the project: The project provides for the construction of the apartment building and its connection to utility networks, as well as the improvement of the adjacent territory and coastline.

Park Inn by Radisson Residence Riga Barona

Sports and Active Recreation Square of the Riga Secondary School No. 84
Squares for skating, basketball, football, volleyball and tennis were improved and equipped. There is also a special square for street gymnastics. The territory is fenced and has paved squares, benches, as well as tracks for both pedestrians and roller skaters.
The total area of improvement works performed by the LNK INDUSTRIES was 56,000 m2, the volume of poured top soil was 5,644.46 m3, greening was performed and a lawn was sown in the area of 30,103.80 m2, stone-block pavement was laid in the area of 7,570 m2, sand in the volume of 5.50 m3 was poured for the long jump pit. The area of each arranged multifunctional sports square is 608 m2 (3 squares in total), the area of the long jump sector is 271.30 m2, and the area of the renovated children's playgrounds is 3,100 m2. A 520-meter long bicycle track, which is also suitable for roller skaters, was improved, while the total length of the improved tracks in the park is 1,460 m.

Cesu 7
Location: 7 Cesu Street, Riga, Latvia
Status: under construction
Description of the project: high-end apartment building. Building’s project includes custom designed apartments with underground parking lot for 30 cars and surface parking for 6 cars. Altogether 32 apartments with area from 56 m2 to 130 m2 are planned in the building. Total living area will amount in 2 400 m2, but commercial premises will occupy 300 m2.

Business centre Hanzas rezidence
Location: 2a Hanzas Street, Riga, Latvia
Status: At the design stage
About: An elegant building complex, which consists of a historical four-storey building with an area of 1,100 m2, which provides an exclusive penthouse on the 4th floor, and a new 7-storey building with spacious terraces and a total area of 3,000 m2.

Residential complex The Pearl
Location: Baltezers, Latvia
Status: The building was comissioned in 2013
About the project: In construction of the Pērle (Pearl) low-rise apartment houses located on the shore of Maza Baltezers lake, LNK Industries implements leading-edge architectural and engineering solutions, combining civil construction with hydraulic engineering construction. The project will be put in commission at the end of this year will contain 65 apartments with full finishing, underground and surface parking lots, a marina and landscaped beach.

Business centre Sporta rezidence
Location: 7 Sporta Street, Riga, Latvia
Status: The building was reconstructed in 2011
About the project: Class A office building with total area of 550 m2.

Scientific laboratory and Scientific Library of Riga Technical University

Residential house Blueberry
Location: Muizas Street 11, Jurmala, Latvia
Status: Comissioned in 2014
About: A residential complex of 59 apartments located in Bulduri.

University of Latvia Academic Center of Natural Sciences
Adress: 1 Jelgavas Street, Riga, Latvia
Status: The building was commissioned in 2015
About: The UL Academic Centre is an important project not only for Latvia, but for the entire Baltic region. One of the most challenging stages is going to be the construction and equipment of the laboratories for the research centres. This will require specific knowledge and complicated technical solutions.

Riga Ukranian Secondary School
Location: 4 Visvalza Street, Riga, Latvia
About the project: Simplified renovation and general construction works of the building, including the façade works, gallery technical project development and gallery construction.

Business centre Alojas rezidence
Status: The building was reconstructed in 2005

Riga Boarding School for the Deaf and Hearing Impaired Children
Location: 21 Graudu Street, Riga, Latvia
Status: Put into commision
About the project: LNK Industries has carried out simplified renovation works, dismantling and mounting, finishing works as well as façade renovation works.

Kindergarten on Slokas Street
Location: 197 Slokas Street, Riga, Latvia
About the project: LNK Industries has carried out simplified renovation works, dismantling and mounting, finishing works as well as façade renovation works.

Business centre Mūkusalas biroji
Location: 6 Biekensalas Street, Riga, Latvia
Status: The building was commissioned in 2002
About: B class office and trade centre. TBA of the centre: 11,000 sq. meters. The building has a parking lot under security surveillance for 200 vehicles.

Residential house Lielupes nams
Location: 18 Lielupes Street, Jurmala, Latvia
Status: The building was commissioned in April 2008
About the project: A comfort class small 4-storey (18 apartments) residential building in the forest, in Jaundubulti, Jurmala. LNK Industries has carried out design and construction of the project, including finishing works and utilities improvement works as well as construction of an underground parking lot.

Residential house Zaubes nams II
Location: 9 Zaubes Street, Riga, Latvia
Status: The building was commissioned inNovember 2008
About: A premium class building with 27 fully finished exclusive apartments. The building was built using the latest technologies and taking into account high requirements to life of modern people. This is a seven-storey building with an underground parking lot for 36 cars, from which two fast yet silent lifts lead to the apartments. The house is equipped with central heating system and heat consumption is significantly reduced due to wall heat isolation, which surpasses the European norms and standards, as well as due to five-chamber windows. which keep the accumulated heat of the sun inside the premises. The luxurious lobby, where a porter waits for you, is located on the ground floor. The house has a spacious courtyard with a playground for children.

Residential house Kalēju nams
Location: 39 Kalēju Street, Jurmala, Latvia
Status: The building was commissioned in May 2011
About: Comfort class 9-apartment building in Melluzi, Jurmala. LNK Industries has carried out design and construction works of the project (strip foundation installation, construction of load-bearing brick walls, production and construction of cast-in-place concrete ceilings, formation of the roof terrace, façade heat insulation, improvement works, installation of engineering networks and carrying out internal finishing works). Kalēju Nams is characterized by a rational and compact apartment layout. Building apartments are equipped with built-in furniture and high-quality plumbing equipment

Business centre Dienvidu vārti I
Location: 74 Darzciema Sreet, Riga, Latvia
Status: At the design stage
About the project: Class B office centre with the total area of 12,000 m2 will be equipped with the latest security and climate management systems and it will have underground parking for 200 cars.

Business centre Dienvidu vārti II
Location: 1 Rezeknes Street, Riga, Latvia
Status: At the design stage
About the project: Class B office centre with the total area of 8,000 m2. LNK Industries carries out planning of the project as well as will perform construction of the building. The building is characterized not only by modern architecture, but also by advanced technological solutions.

Residential house Dārzciema nams
Location: 24a Strautu Street, Riga, Latvia
Status: At the design stage
About the project: Comfort Class 5-storey (42 apartments) house in a quiet area in Darzciems, Riga. LNK Industries carries out design of the building as well as the company will perform its construction, finishing works (individual designs are offered to customers), kitchen and bathroom improvement. Underground parking places will be provided.

Residential house Briāna nams
Location: 11 Briana Street, Riga, Latvia
Status: At the design stage
About the project: Business class residential building with 29 apartments in the historic centre of Riga. LNK Industries carries out design of the project. The company will also execute construction, full finishing and improvement of the building as well as construction of an underground parking lot.

Aloja Business Centre
Location: 62 Kr. Valdemara, Riga, Latvia
Status: The building was put in commission in May 2009.
Description of the project: Modern class A office centre with total area of 15,000 m2. Alojas Biznesa Centrs uses unique technological solutions, making the building more environmentally friendly and energy-saving (Alojas Biznesa Centrs has received a green certificate for the building's compliance with all ecological and energy-saving standards, as well as in 2012, the building was awarded the prize as the most energy-efficient building in Latvia in 2011). A number of automated building management and energy-saving technologies are introduced here, which significantly affects consumption of various resources (heat, electricity, etc.). When constructing the Alojas Biznesa Centrs, for the first time in the history of Latvia, in such dense urban development area the underground parking lot for 180 cars was arranged on three floors at the depth of 18 metres.

Business centre Dārzciema biroji
Location: 60 Darzciema Street, Riga, Latvia
Status: Put into operation in 2011.
About: Dārzciema Biroji is a B class office centre with the total area of 6 000 m2 and free on ground parking for 200 vehicles.

Mercedes-Benz centre
Location: 5 Abrenes Street, Riga, Latvia
About the project: Construction of the autocentre, including the frame construction from metal structures and cast-in-place concrete ceilings, construction of decorative concrete walls, installation of engineering networks, improvement and final finishing.

Residential house Ģertrūdes nams
Location: 18 Gertrudes Street, Jurmala, Latvia
About the project: Comfort class 3-storey (20 apartments) residential building project. LNK Industries has carried out design and construction of the building, including installation of piles, cast-in-place reinforced concrete foundation, the building frame and load-bearing walls, prefabricated reinforced concrete ceiling slabs and engineering networks. The building's compact design allows the targeted use of the apartment area. Apartments are fully finished, as well as kitchens of all apartments are equipped with modern appliances, while bathrooms – with high-quality sanitaryware.

TC Draudzība
Location: 32 Tilta Street, Sarkandaugava, Riga, Latvia.
Status: Was put in commission in 2013.
About the project: shopping centre of 1,500 square meters, which houses 15 retail shops, including Rimi food retailer.

TTS (Transportation technology systems) plant
Location: 60 Darzciema Street, Riga, Latvia

Cemex cement factory
Location: Broceni, Latvia
Status: The object was put into operation in 2009
Project description: One of the most advanced concrete factories in the Europe, which at the same time complies with internationally adopted environmental standards. On Cemex plant, LNK Industries specialists for the first time in Latvia applied slide-mould technology to secure ongoing concreting, which resulted in building of a 60 meter high tower in 22 days.

Industrial park Vangažu industriālais parks
Location: 24/34 Gaujas Street, Vangazi, Latvia
Status: The object has been put into operation

Waste management complex Getliņi EKO
Location: 57 Kaudzisu Street, Rumbula, Stopini District, LV-2121, Latvia
About the project: In 2001, AS LATVIJAS TILTI, a company of the LNK Industries construction and production group, by the order of SIA Getliņi EKO and design of SIA Geo Consultants and Swedish company SWECO, has implemented the first stage of conservation of the waste landfill of 35 hectare created during the Soviet Union time, in order to prevent environmental pollution in the old part of the waste landfill and ensure environmentally-friendly waste management according to international standards, as well as create an alternative energy source. AS LATVIJAS TILTI is the first company, which began implementation of the reclamation project in Latvia. The Getliņi EKO project implemented in Stopinu Region has no equivalent in Latvia in terms of scale. Nowadays, this technology is widely used in a number of countries around the world, especially in the Scandinavian countries, making it possible to manage waste in environmentally-friendly way and at the same time to use the territory both for alternative energy production and for livestock growing and agricultural work. The works executed by AS LATVIJAS TILTI included waste levelling and creation of the protective layer of clay above the waste of 0.5 metre thick with a total volume of 180,000 m3, thus preventing the escape of harmful gases into the environment. The protective layer is covered with soil and grass is planted on it to provide a visually appealing environment design and functionality – the possibility to grow plants or feed cattle. A so called foot drain is arranged around the mountain of waste that serves as a barrier to the shallow groundwater contamination. The company has also made 172 vertical drill holes to a depth of 30 m with diameter up to 50 cm, as well as installed the pipeline that connects the holes with gas power station. Gases that appear as a result of the waste biodegradation are isolated from the environment, delivered to the power unit by the pipeline system and burned in internal combustion engines, which provide production of alternative electrical energy and thermal energy for economic activities, including heating of greenhouses. Four gas regulation stations have been installed to ensure high-quality gas composition. AS LATVIJAS TILTI has also implemented construction of IB and IIIA biodegradation cells. Waste is kept and biogas energy is produced in 90x180 m large, moisture-proof biodegradation cells.

Industrial park Baltijas industriālais parks
Location: 7 Piedrujas Street, Riga, Latvia

Aircraft testing laboratory
Location: 1 Rezeknes Street, Riga, Latvia
About: AVIATEST specialises in field rig testing of aerotechnics (frames of aeroplanes, helicopters and their aggregates). The centre also tests airport equipment (aircraft hydraulic jacks, torque wrenches etc.) and various building constructions.

Club Central Residence
Location: Baznicas Street, Riga, Latvia
Status: The building was commissioned in 2015
About the project: 2 100 m² of glass have been used for façade of the Club Central Residence residential building and totally 140 tons of reinforcement bars have been used for the building. Total area of the complex is 2218 m².

Stadium on Rušonu Street
Location: 6 Rušonu Street, Riga, Latvia
Status: construction in progress
About the project: the stadium construction and area improvement works on the territory used by the Riga Secondary School No. 25. The territory will host a football field with artificial grass covering, running track and long jump sector, streetball field, two multifunctional fields and children’s playground for the pupils and residents of the Ķengarags area.

Leisure and sports complex at 116ª Barona Street
Location: 116ª Barona Street, Riga, Latvia
Status: construction works in progress
Description of the site: the stadium construction and improvement works at the leisure and sports complex at 116ª Barona Street

State Police and Riga Municipal Police station

Metal structures
Metal structures are being produced in the workshops of LNK Industries for our own projects as well as made on commission for bridges, frames of marine constructions (wharves and piers), ironworks for production facilities and civil engineering projects.
The production facilities are located in Riga and encompass an area of 10,000 sq. metres. They boast modern welding equipment, including automatic welding machines, semi-automatic machines and robots, automatic metal processing and metal cutting machines, as well as large capacity painting and shot blasting chambers, fitted with state-of-the-art equipment. We employ 50 welders with international certificates to carry out demanding tasks.
Production facilities have cranes at their disposal with a hoisting capacity of up to 30 tons. Railway spur tracks with our own shunting engines and the proximity of motorways facilitate the delivery of any production to the site.
To guarantee both the accuracy and efficiency of assembling works on the customer’s site, in particularly challenging circumstances, our specialists perform an on-site test assembly of complex items to elaborate the end assembling technologies down to the minor details.

Ferroconcrete structures
Production of ferroconcrete (reinforced concrete) structures is the very basis of the contemporary building industry, which is true with regard to infrastructure, industrial or public construction projects alike. Prefabrication of structures at a plant cuts down the assembly costs and shortens the production period.
LNK Industries manufactures reinforced concrete structures, both for its own projects and on commission by offering a wide range of standard products, manufactures ferroconcrete structures such as prism piles, panels and slabs for building and bridge construction. We also produce non-standard customised reinforced concrete structures, such as borders, barriers, staircases, etc., and guarantee the manufacturing of any structure precisely, according to the customer's specifications.
The production facilities take up an area of 5,000 sq. metres and have their own concrete plant and a special specimen testing laboratory. We have equipment at our disposal for the manufacturing of steel frames, casing for standard and non-standard reinforced concrete items as well as steaming chambers. 25 people are employed in production.

Aero-concrete manufacturing plant AEROC
Location: Saulkalne, Latvia
Status: The object has been put into operation
Project description: LNK Industries conducted designing and construction of the plant as well as installation of conveyance technology systems.

Machinery fleet
Description: LNK Industries has at its disposal a fleet of construction and auxiliary equipment, which ensures an ongoing production process and optimizes the expenses.
LNK Industries has its own concrete plant and more than 100 units of mobile machinery: concrete trucks, concrete pumps, mobile and stationary cranes, pile-driving machines, bulldozers, excavators, prime movers, specialized transportation platforms, etc. Many of the above machines are unique and accessible in very limited quantity in the Baltic countries.
The high-capacity machinery stock guarantees that LNK Industries always performs works in due quality and by the set deadlines, while complying with environmental requirements and exercising due care with regard to utilization of resources.
All LNK Industries machines are fully staffed with highly qualified operators and are capable of working in a three-shift mode.
The company’s own construction equipment fleet gives us a strong competitive edge and our customers can depend upon us to fulfill their orders in short term and at lower expenses, whilst being assured that the contractor will keep its promises. This is why LNK Industries constantly upgrades its technological capacities, as during the past five years over €5 million have been earmarked for these purposes.